(Summary description)In March 2021, Minister Yan of our company signed a set of GDM326 friction pulley lining for JKMD4*4 Mining hoist.At the end of April, GDM326 friction Koepe liner was successfully delivered to the mine site.
Gdm326 friction pulley lining installation process
(Summary description)In March 2021, Minister Yan of our company signed a set of GDM326 friction pulley lining for JKMD4*4 Mining hoist.At the end of April, GDM326 friction Koepe liner was successfully delivered to the mine site.
- Categories:News
- Author:
- Origin:
- Time of issue:2021-05-14
- Views:0
In March 2021, Minister Yan of our company signed a set of GDM326 friction pulley lining for JKMD4*4 Mining hoist.At the end of April, GDM326 friction Koepe liner was successfully delivered to the mine site.
On May 10, due to uncontrollable reasons, the mine's original installation company was unable to install on time, but the shutdown maintenance plan has been submitted. If it is not installed on time, it will have a huge impact on the mine.
After receiving the call for helping from the mine, Yan reported to the company leaders.
The leaders attached great importance and gave full support to the installation, and immediately began to arrange personnel, tools and other installation tools.
At 7:00 a.m. on May 12, the temporary installation team of Zhongshi technology set out with the first ray of sunshine in the morning and arrived at the mine at 6:00 p.m. that day. It started work all night, setting up worktables, taking tools, coordinating personnel with the mine, and assisting tooling.